Procedure Change of Land use
Procedure for Change of Land Use from the one proposed in the Master Plan (U/s 14-A of the Karnataka Town and Country Planning Act, 1961) As per Govt. Guideline. No. UDD 165 BMR 2012 Dated: 12.10.2012).
1. The owner or the legal entity of the land who intends to develop his land for the purpose other than that earmarked in the approved Master Plan, has to make an application, along with relevant documents, to the concerned Planning Authority for consideration.
2. The authority shall, after verification as per the guidelines issued by the Government, if it finds that the changes sought are relevant to planning principles and are in public interest and are not in contravention to any other statute will publish the proposal in one or more daily newspapers, inviting objections/ comments from the public within a period of not less than fifteen days.
3. The Authority then reviews the Change of Land Use proposal with the public objections received if any and passes a resolution, recording reasons, regarding its consideration or non-consideration for change in Land use.
4. The CLU cases considered by the Authority are submitted to the Government for approval through Bangalore Metropolitan Region Development Authority, Bangalore. The Government, with the technical opinion of the Bangalore Metropolitan Region Development Authority passes order approving or rejecting the case, as it thinks fit. The Authority and the owner of the land shall abide by such Government order.
List of Documents required for Change of Land Use:-
1. Sale deed / Partition deed, Latest EC in form no-15 and 16.
2. Latest copy of Records of Right (RTC), Copy of Mutation/ Khata certificate and Land Acquisition Details if any,
3. Original Survey sketch issued by the concerned Asst. Director of land records showing all-round measurements of the land, conversion order number and date, details of the abutting / connecting public road, alignment of HT line, details of A & B Kharab including all round boundary schedule of the proposed land.
4. Village map showing the proposed land duly certified by the concerned Asst. Director of land records.
5. Site plan showing the surrounding details of development around 500 mts. radius with an interval of 50 mts. from the boundary of the property.
6. Certification from the concerned revenue authority regarding PTCL & 79(a), (b) Case under Karnataka Land Reforms Act, 1964.
7. Google image showing land in question and surrounding developments upto 500 mts. from the boundary of the property.
8. Public Approach road details (viz. classification of road, width of road etc.)
9. Approved Master plan extract showing the land in question.
10. The following notarized Declaration affidavits has to be submitted by the applicant:-
a) Whether the proposed land was de-notified from any of the land acquisition notifications issued by the government for public purposes.
b) Declaration letter confirming there is no any other cases are pending in the Courts/ Lokayuktha office on the land in question.
c) Details of public interest involved in the proposed change of land proposal.
Source: Hoskote TPA, GoK.